p.5742025 Nonresidential Appendices (a) Separately list all requirements for each PAF that is claimed in accordance with
p.574applicable Sections 110.9, and 140.6(a)2, Table 140.6-A, 170.2(e)2B, and Table 170.2-L.
p.574(b) Verify the installation complies with all applicable requirements in accordance with
p.574applicable Sections 110.9, and 140.6(a)2, Table 140.6-A, 170.2(e)2B, and Table 170.2-L.
p.574(c) If all of the above items are not true for a specific PAF, the installation fails, and
p.574that specific PAF cannot be used.
p.574(d) For lighting systems that are claiming a PAF for daylight continuous dimming plus
p.574OFF control in accordance with Section 140.6(a)2H and 170.2(e)2Bviii, the system must successfully complete the functional performance test in Section NA 7.6.1.3, and in addition during the Full Daylight Test the controls shall automatically turn OFF the luminaires that are receiving the daylight continuous dimming plus OFF PAF credit.
p.574NA7.7.6 Lighting for a Videoconferencing Studio in Accordance with Section 140.6(c)2Gvii
p.574NA7.7.6.1 Installation Inspection
p.574Verify and document the following:
p.574(a) The videoconferencing studio is using only the Area Category Method for
p.574compliance. The extra lighting allowance shall not be taken when using the Complete Building Method or Tailored Method of compliance.
p.574(b) The videoconferencing studio is a room with permanently installed
p.574videoconferencing cameras, audio equipment, and playback equipment for both audio-based and video-based two-way communication between local and remote sites.
p.574(c) General lighting is switched in accordance with Table 130.1-A.
p.574(d) Wall wash lighting is separately switched from the general lighting system.
p.574(e) All of the lighting is controlled by a multiscene programmable control system
p.574(scene preset control system).
p.574(f) If all of the above is not true, the installation fails, and the extra wattage for
p.574videoconferencing studio lighting cannot be used.
p.574Outdoor Lighting Controls Acceptance Tests
p.574NA7.8.1 Motion Sensing Controls Acceptance Tests
p.574NA7.8.1.1 Construction Inspection
p.574Prior to functional testing, verify and document the following:
p.574(a) The motion sensing controls are shown on plan documents and are installed.
p.574Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes