p.5772025 Nonresidential Appendices Refrigerated Warehouse Refrigeration System Acceptance Tests
p.577The measurement devices used to verify the refrigerated warehouse controls shall be calibrated once every two years using a NIST traceable reference. The calibrated measurement devices to be used in these acceptance tests are called the "standard" and shall have the following measurement tolerances: The temperature measurement devices shall be calibrated to +/- 0.7°F between -30°F and 200°F. The pressure measurement devices shall be calibrated to +/- 2.5 psi between 0 and 500 psig. The relative humidity (RH) measurement devices shall be calibrated to +/- 1% between 5% and 90% RH.
p.577NA7.10.1 Electric Resistance Underslab Heating System
p.577NA7.10.1.1 Construction Inspection
p.577Prior to functional testing, verify and document the following for all electric resistance underslab heating systems:
p.577(a) Verify that summer on-peak period is programmed into all underslab heater
p.577controls to meet the requirements of Section 120.6(a)2.
p.577NA7.10.1.2 Functional Testing
p.577Step 1: Using the control system, lower slab temperature setpoint. Verify and document
p.577the following using an electrical test meter:
p.577(a) The underslab electric resistance heater is off.
p.577Step 2: Using the control system, raise the slab temperature setpoint. Verify and document the following using an electrical test meter:
p.577(b) The underslab electric resistance heater is on.
p.577Step 3: Using the control system, change the control system’s time and date
p.577corresponding to the local utility’s summer on-peak period. If control system only accounts for time, set system time corresponding to the local utility’s summer on- peak period. Verify and document the following using an electrical test meter:
p.577(c) The underslab electric resistance heater is off.
p.577Step 4: Restore system to correct schedule and control setpoints.
p.577NA7.10.2 Evaporators and Evaporator Fan Motor Variable Speed Control
p.577NA7.10.2.1 Construction Inspection
p.577Prior to functional testing, document the following on all evaporators:
p.577(a) All refrigerated space temperature sensors used for control are verified to read
p.577accurately (or provide an appropriate offset) using a temperature standard.
p.577(b) All refrigerated space humidity sensors used for control are verified to read
p.577accurately (or provide an appropriate offset) using a humidity standard.
p.577Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes