p.6032025 Nonresidential Appendices NA7.18.4 Rated Central Ventilation System Heat Recovery or Energy Recovery Acceptance
p.603The objective of this procedure is to verify the heat recovery ventilation (HRV) or energy recovery ventilation (ERV) requirement in multifamily buildings for compliance with Section 170.2(c)3Bivb, a central ERV/HRV serving multiple dwelling units.
p.603NA7.18.4.1 Construction Inspection
p.603Prior to functional testing, verify and document the following:
p.603a) Confirm the total design ventilation airflow rate for the dwelling units served by the central ventilation system as required by Section 160.2(b)2Av.
p.603b) Visually confirm that an ERV/HRV is installed and record the make and model.
p.603NA7.18.4.2 Functional Testing
p.603Step 1: Verify that the ERV/HRV can provide the airflow rate that meets the design ventilation airflow rate by checking its product specifications.
p.603Step 2: Verify that the ERV/HRV’s nominal sensible recovery efficiency is 67 percent or greater, by checking its product specifications or databases such as HVI, AHRI, etc.
p.603Step 3: Verify that the ERV/HRV can meet the fan power requirements of Section 170.2(c), by checking its product specifications or databases such as HVI, AHRI, etc.
p.603Step 4: Verify that the ERV/HRV has a recovery bypass or free cooling function by visual inspection and checking its product specifications. Verify that its recovery bypass or free cooling control capabilities meet the requirements in Section 170.2, Table 170.2-G.
p.603Step 5: Conduct functional testing of the bypass function according to NA7.5.4.
p.603Steam Trap Fault Detection Acceptance Tests
p.603NA7.19.1 Steam Trap Fault Detection
p.603Acceptance tests for steam trap fault detection in accordance with Section 120.6(i).
p.603NA7.19.1.1 Construction Inspection
p.603Verify and document the following steam trap system capabilities prior to functional testing:
p.603a) Distribution system steam trap arrangement and connected steam line operating
p.603pressure subject to 120.6(i) were installed as designed including the presence of monitoring equipment, strainer, and blow-off valve.
p.603Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes