p.4482025 Residential Appendices RA4.2.2.4 Documentation at Occupancy
p.448The following documentation shall be made available to the building owner at occupancy:
p.448(a) Completed and signed Installation Certificate form(s);
p.448(b) A 10 or more year Warranty Certificate(s) shall be given to the building owner for
p.448fenestration products other than window films.
p.448RA4.3 HVAC Measures
p.448RA4.3.1 Evaporatively-Cooled Condensing Units
p.448To ensure reliable energy savings and proper operation and control, the evaporatively-cooled condensing unit shall conform to the requirements in section RA4.3.1.
p.448The verifications and eligibility testing listed in sections RA4.3.1.1 and RA4.3.1.2 shall be completed, certified by the HVAC installer on the Certificate of Installation, and verified by a ECC- Rater on the Certificate of Verification.
p.448The builder or installer shall provide a Certificate of Compliance that reports the use of an evaporatively-cooled condensing unit for determining performance standards compliance, that requires verification of the system equipment, duct sealing, and refrigerant charge for compliance as described in Section RA4.3.1.1.
p.448RA4.3.1.1 Verification
p.448The following shall be verified by a ECC-rater and reported on a Certificate of Verification for the system:
p.448(a) EER2 at 95 o F dry bulb and 75 o F wet bulb temperature is listed with ARI (generally called
p.448EERa).
p.448(b) EER2 at 82 o F dry bulb and 65 o F wet bulb temperature is submitted to ARI and published
p.448by the manufacturer in accordance with ARI guidelines (generally called EERb).
p.448(c) Presence of TXV is verified if the ARI certified EER2s are based on equipment with TXVs.
p.448(d) Ducts are tested and sealed in all installations of this equipment according to applicable
p.448requirements in Section RA3.1.
p.448(e) Proper refrigerant charge or presence of Fault Indicator Display (FID) is verified if
p.448compliance credit is taken for this measure when TXVs are not installed.
p.448RA4.3.1.2 Eligibility Testing Eligibility Testing
p.448The installing contractor shall complete the following eligibility testing and document the results on the applicable Certificate of Installation.
p.448(a) Verify that there is water in the water casing.
p.448(b) Switch on the cooling system by setting the thermostat below the room temperature.
p.448(c) Verify that the water pump starts running when the system is turned on.
p.448– Eligibility Criteria for Energy Efficiency Measures