p.5302025 Nonresidential Appendices (c) ASTM E 903 test results and, if applicable, ASTM E1175 results should also be
p.530retained by the building owner.
p.530Mechanical Systems Acceptance Tests
p.530NA7.5.1 Outdoor Air
p.530NA7.5.1.1 Variable Air Volume Systems Outdoor Air Acceptance
p.530NA7.5.1.1.1 Construction Inspection
p.530Prior to functional testing, verify and document the following:
p.530(a) Sensor used to control outdoor air flow is either factory calibrated or field
p.530calibrated.
p.530(b) Attach calibration certification or results.
p.530(c) Dynamic damper control is being used to control outside air.
p.530(d) Specify the type of dynamic control being utilized to control outside air.
p.530(e) Specify the method of delivering outside air to the unit.
p.530(f) Pre-occupancy purge has been programmed to meet the requirements of
p.530Standards §120.1(d)2.
p.530NA7.5.1.1.2 Functional Testing
p.530Step 1: If the system has an outdoor air economizer, force the economizer high limit to
p.530disable economizer control (e.g., for a fixed drybulb high limit, lower the setpoint below the current outdoor air temperature).
p.530Step 2: Adjust supply airflow to achieve design airflow or maximum airflow at full cooling.
p.530Verify and document the following:
p.530(a) Measured outside airflow reading is within 10 percent of the total ventilation air
p.530called for in the Certificate of Compliance.
p.530(b) Outside air damper position stabilizes within 5 minutes.
p.530Step 3: Adjust supply airflow to either the sum of the minimum zone airflows, full heating,
p.530or 30 percent of the total design airflow. Verify and document the following:
p.530(a) Measured outside airflow reading is within 10 percent of the total ventilation air
p.530called for in the Certificate of Compliance.
p.530(b) Outside air damper position stabilizes within 5 minutes.
p.530Step 4: Restore system to “as-found” operating conditions.
p.530NA7.5.1.2 Constant Volume System Outdoor Air Acceptance
p.530NA7.5.1.2.1 Construction Inspection
p.530Prior to Functional Testing, verify and document the following:
p.530Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes