p.5292025 Nonresidential Appendices 1. Verify the horizontal (not diagonal or vertical) distance from the front edge of the exterior light shelf to the back edge of the exterior light shelf matches the building plans;
p.5292. verify the vertical (not diagonal or horizontal) distance from the lowest edge of the exterior light shelf to the sill of the window below it matches the building plans;
p.5293. If the exterior light shelf is less than two feet below the clerestory windowsill, verify the visible reflectance on the ASTM E903 test results matches the building plans;
p.529(e) Verify that light shelves are installed at the height specified in the building plans;
p.529(f) Installation of light shelves shall meet the manufacturer’s installation instructions;
p.529(g) After the installation the installer completes and signs the Declaration Statement
p.529on the Certificate of Installation. A signed copy of the Certificate(s) shall remain at the job site for verification by the building inspector.
p.529NA7.4.6.3 Field Technician or Responsible Person Shall Meet the Following Protocols After Installation:
p.529(a) Verify the Certificate of Installation and the Declaration Statement is signed before
p.529inspection of the installation; and
p.529(b) If there is any window area below the interior light shelf on the same floor, then
p.529verify there is an exterior light shelf above that window area.
p.529(c) Verify that that the light shelf is permanently mounted;
p.529(d) Verify the light shelf extends beyond each side of the window jamb by the length
p.529shown on the building plans;
p.529(e) Verify that interior light shelves are horizontal;
p.529(f) If there is an exterior light shelf, verify that the exterior light shelf is horizontal or
p.529slopes downwards from the window;
p.529(g) After light shelves inspection is completed, complete the Certificate of Acceptance
p.529Test and sign the Declaration Statements of the certificate; and
p.529(h) Provide certificates and additional copies to the builder, enforcement agency and
p.529building owner at occupancy.
p.529NA7.4.6.4 Documentation at Occupancy:
p.529The following documentation shall be made available to the responsible party of construction or building owner at occupancy;
p.529(a) A completed and signed copy of the Certificate of Installation and the Certificate of
p.529Acceptance Test, form(s);
p.529(b) If supplied by the manufacturer, a copy of the manufacturer’s warranty and user
p.529manual;
p.529Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes