p.5282025 Nonresidential Appendices NA7.4.5.4 Documentation at Occupancy:
p.528The following documentation shall be made available to the responsible party of construction or building owner at occupancy;
p.528(a) A completed and signed copy of the Certificate of Installation and the Certificate of
p.528Acceptance Test, form(s);
p.528(b) If supplied by the manufacturer, a copy of the manufacturer’s warranty and user
p.528manual;
p.528(c) ASTM E903 test results and, if applicable, ASTM E1175 results should also be
p.528retained by the building owner.
p.528NA7.4.6 Interior and Exterior Light Shelves for PAF
p.528NA7.4.6.1 Procedures
p.528These procedures detail the installation and verification protocols necessary to meet acceptance requirements of interior and exterior light shelves for PAF. In addition, the responsible person shall fill out Certificate of Acceptance. The responsible person shall verify the light shelf to be installed matches the energy compliance documentation (Certificate of Compliance) and building plans. A copy of the Installation and Acceptance certificate shall be given to the building owner and the enforcement agency for their records.
p.528For buildings with up to seven (7) light shelf units claiming the Interior and Exterior Light Shelves for PAF, all light shelf units shall be tested. For buildings with more than seven (7) light shelf units claiming the PAF, random sampling may be done to select the seven light shelf units. If any of the light shelf units in the sample group or seven light shelf units fails the acceptance test, another group of seven light shelf units must be tested.
p.528Each interior light shelf shall be provided with documentation of visible reflectance testing per ASTM E903. Exterior light shelves may be provided with documentation of visible reflectance testing per ASTM E903. The documentation shall be located at the job site for verification by the enforcement agency.
p.528NA7.4.6.2 The Responsible Person or Installer Shall Meet the Following Protocols before Installation:
p.528(a) Verify the horizontal (not diagonal or vertical) distance from the front edge of the
p.528interior light shelf to the back edge of the light shelf matches the building plans;
p.528(b) Verify the vertical (not diagonal or horizontal) distance from the highest edge of the
p.528interior light shelf to the top of the clerestory window above it matches the building plans;
p.528(c) Verify the visible reflectance on the ASTM E903 test results of the interior light
p.528shelf matches the building plans;
p.528(d) If there is an exterior light shelf:
p.528Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes