p.5702025 Nonresidential Appendices NA7.6.4.2.2 Method 2: Verification of Systems Already Tuned
p.570Step 1: Measurement of tuned lighting system
p.570(a) Set all lighting controls except institutional tuning controls to provide maximum
p.570output of tested system. Controls set to maximum light output include but not limited to manual dimmers, multilevel occupant sensing, and automatic daylighting controls.
p.570(b) Measure full light output at location where most of the illuminance is due to the
p.570controlled lighting or measure power draw of the controlled lighting. Current measurements may be used instead of power measurements.
p.570Step 2: Measurement of lighting system with institutional tuning overriden
p.570(a) Reset institutional tuning controls to allow full light output. Set all lighting controls
p.570to provide maximum output of tested system including but not limited to institution tuning control, manual dimmers, multilevel occupant sensing, and automatic daylighting controls.
p.570(b) Measure full light output at the same location as in Step 1 or measure the power
p.570draw of the same circuit as in Step 1. Current measurements may be used instead of power measurements.
p.570(c) If the light output or power draw measured in Step 1(b) is 85% or less of the light
p.570output or power draw measured in Step 2(b), the system passes this test; otherwise, the system fails this test.
p.570Step 3: Restore Institutional Tuning settings
p.570(a) If the tested system passed the test in Step 2, restore the institutional tuning
p.570settings.
p.570NA7.6.5 Demand Responsive Controls – Controlled Receptacles
p.570NA7.6.5.1 Construction Inspection
p.570Prior to functional testing, verify and document the following:
p.570(a) The demand responsive control is setup to communicate in one of the following
p.570communication protocols: Wi-Fi, ZigBee, BACnet, Ethernet or other wired or wireless bi-directional communication pathway according to the requirements in Standards § 110.12. The demand responsive control is setup to communicate for the functional testing of NA7.6.5.2.
p.570(b) Verify that demand responsive controlled receptacles are installed.
p.570(c) Verify that the receptacle has a permanent and durable marking for controlled
p.570receptacles or circuits to differentiate them from uncontrolled receptacles or circuits.
p.570(d) Verify the receptacle is controlled by an automatic shut-off control.
p.570Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes