p.5412025 Nonresidential Appendices (b) Verify that this is within 5 percent of the submittal data for the pump.
p.541Step 2: Reopen the pump discharge isolation valves. Automatically close all valves on the
p.541systems being tested. If 3-way valves are present, close off the bypass line. Verify and document the following:
p.541(c) The valves automatically close.
p.541(d) Record the pressure differential across the pump.
p.541(e) Verify that the pressure differential is within 5 percent of the reading from Step 1
p.541for the pump that is operating during the valve test.
p.541Step 3: Restore system to correct operating conditions.
p.541NA7.5.8 Supply Water Temperature Reset Controls
p.541NA7.5.8.1 Construction Inspection
p.541Prior to Functional Testing, verify and document the following:
p.541(a) Supply water temperature sensors have been either factory or field calibrated.
p.541NA7.5.8.2 Functional Testing
p.541Step 1: Change reset control variable to its maximum value. Verify and document the
p.541following:
p.541(a) Chilled or hot water temperature setpoint is reset to appropriate value.
p.541(b) Verify that actual supply temperature changes to within 2 percent of the new
p.541setpoint.
p.541Step 2: Change reset control variable to its minimum value. Verify and document the
p.541following:
p.541(c) Chilled or hot water temperature setpoint is reset to appropriate value.
p.541(d) Verify that actual supply temperature changes to within 2 percent of the new
p.541setpoint.
p.541Step 3: Restore reset control variable to automatic control. Verify and document the
p.541following:
p.541(e) Chilled or hot water temperature set-point is reset to appropriate value.
p.541(f) Verify that actual supply temperature changes to within 2 percent of the new
p.541setpoint.
p.541NA7.5.9 Hydronic System Variable Flow Controls
p.541NA7.5.9.1 Construction Inspection
p.541Prior to Functional Testing, verify and document the following:
p.541(a) The static pressure location, setpoint, and reset control meets the requirements of
p.541the Standards Section 140.4(k)6B.
p.541Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes