NA7.5.6.1 Construction Inspection

p.5402025 Nonresidential Appendices NA7.5.6 Supply Fan Variable Flow Controls

p.540NA7.5.6.1 Construction Inspection

p.540Prior to Functional Testing, verify and document the following:

p.540(a) Supply fan includes device(s) for modulating airflow, such as variable speed drive

p.540or electrically commutated motor.

p.540(b) For multiple zone systems:

p.5401. Discharge static pressure sensors are either factory calibrated or field- calibrated.

p.5402. The static pressure location, setpoint, and reset control meets the requirements of §140.4(c)2A and §140.4(c)2B.

p.540NA7.5.6.2 Functional Testing

p.540Step 1: Simulate demand for full design airflow. Verify and document the following:

p.540(a) Supply fan controls modulate to increase capacity.

p.540(b) For multiple zone systems, supply fan maintains discharge static pressure within

p.540+/-10 percent of the current operating setpoint.

p.540(c) Supply fan controls stabilize within a 5 minute period.

p.540Step 2: Simulate demand for reduced or minimum airflow. Verify and document the following:

p.540(d) Supply fan controls modulate to decrease capacity.

p.540(e) Current operating setpoint has decreased (for systems with DDC to the zone

p.540level).

p.540(f) For multiple zone systems, supply fan maintains discharge static pressure within

p.540+/-10 percent of the current operating setpoint.

p.540(g) Supply fan controls stabilize within a 5 minute period.

p.540Step 3: Restore system to correct operating conditions.

p.540NA7.5.7 Valve Leakage Test

p.540NA7.5.7.1 Construction Inspection

p.540Prior to Functional Testing, verify and document the following:

p.540(a) Valve and piping arrangements were installed as specified by the design drawings.

p.540NA7.5.7.2 Functional Testing

p.540Step 1: For each of the pumps serving the distribution system, dead head the pumps

p.540using the discharge isolation valves at the pumps. Document the following:

p.540(a) Record the differential pressure across the pumps.

p.540Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes