p.5422025 Nonresidential Appendices (b) Pressure sensors are either factory or field calibrated.
p.542NA7.5.9.2 Functional Testing
p.542Step 1: Modulate control valves to reduce water flow to 50 percent of the design flow or
p.542less, but not lower than the pump minimum flow. Verify and document the following:
p.542(a) Pump operating speed decreases (for systems with DDC to the zone level).
p.542(b) Current operating setpoint has not increased (for all other systems that are not
p.542DDC).
p.542(c) System pressure is within 5 percent of current operating setpoint.
p.542(d) System operation stabilizes within 5 minutes after test procedures are initiated.
p.542Step 2: Open control valves to increase water flow to a minimum of 90 percent design
p.542flow. Verify and document the following:
p.542(e) Pump speed increases.
p.542(f) Pumps are operating at 100 percent speed.
p.542(g) System pressure is greater than the setpoint in Step 1.
p.542(h) System pressure is within ±5 percent of current operating setpoint. System
p.542operation stabilizes within 5 minutes after test procedures are initiated.
p.542Step 3: Restore system to correct operating conditions.
p.542NA7.5.10 Automatic Demand Shed Control Acceptance
p.542NA7.5.10.1 Construction Inspection
p.542Prior to Acceptance Testing, verify and document the following:
p.542(a) That the EMCS interface enables activation of the central demand shed controls.
p.542NA7.5.10.2 Functional Testing
p.542Step 1: Engage the global demand shed system. Verify and document the following:
p.542(a) That the cooling setpoint in non-critical spaces increases by the proper amount.
p.542(b) That the cooling setpoint in critical spaces do not change.
p.542Step 2: Disengage the global demand shed system. Verify and document the following:
p.542(c) That the cooling setpoint in non-critical spaces return to their original values.
p.542(d) That the cooling setpoint in critical spaces do not change.
p.542Step 3: Return system to normal operating conditions.
p.542Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes