p.5552025 Nonresidential Appendices additional 5 minute time delay after occupant sensing controls have indicated all rooms served by the zone are unoccupied before resetting zone temperature setpoints and shutting off zone ventilation air).
p.555Step 8: Confirm that no ventilation is being supplied to the space with the occupant
p.555sensor.
p.555Step 9: Put the zone in pre-occupancy ventilation mode (i.e., adjust the occupancy
p.555schedule to one hour prior to normal scheduled occupancy).
p.555Step 10: Physically vacate all spaces served by the zone.
p.555Step 11: Confirm that within 5 minutes of occupant sensing controls indicating that
p.555all spaces served by the zone are unoccupied, the zone is supplied with pre-occupancy ventilation rate of Section 120.1(d)2: either the minimum rate of outdoor air required by Section 120.1(c) or three complete air changes is supplied to the zone during the one hour period immediately before the zone is scheduled to be occupied. (See Step 7 concerning maximum occupant sensing control time delay).
p.555Step 12: Occupy a space served by the zone during the one hour immediately
p.555prior to scheduled occupancy. Confirm that the zone is supplied with pre occupancy ventilation rate of Section 120.1(d)2.
p.555Step 13: Restore the system to normal operation.
p.555NA7.5.18 Cooling Tower Conductivity Controls
p.555The following acceptance tests apply to all open- and closed-circuit cooling towers.
p.555NA7.5.18.1 Construction Inspection
p.555Prior to functional testing, verify and document the following:
p.555(a) The conductivity controls, makeup water flow meter(s), and overflow alarms are
p.555installed as specified on the plans.
p.555(b) Maximum achievable cycles of concentration are documented on the NRCC
p.555MCH-E compliance document.
p.555(c) Blowdown control sequence is available and documented in the building
p.555documents.
p.555(d) Controls are programmed to automate bleed to the maximum cycles of
p.555concentration documented on the NRCC-MCH-E form.
p.555(e) Controls shall be programmed not to allow blowdown until one or more of the
p.555parameters in Table NA7 reaches the value specified in NRCC-MCH-E.