p.5482025 Nonresidential Appendices Step 3: Verify that after the supply air temperature is reset up to the maximum setpoint, the airflow rate then increases up to the heating maximum flow rate in order to meet the heating load.
p.548NA7.5.13 Distributed Energy Storage DX AC Systems Acceptance Tests2F 3
p.548These acceptance requirements apply only to constant or variable volume, direct expansion (DX) systems with distributed energy storage (DES/DXAC). These acceptance requirements are in addition to those for other systems or equipment such as economizers, packaged equipment, etc.
p.548NA7.5.13.1 Construction Inspection
p.548Prior to Performance Testing, verify and document the following:
p.548(a) The water tank is filled to the proper level.
p.548(b) The water tank is sitting on a foundation with adequate structural strength.
p.548(c) The water tank is insulated, and the top cover is in place.
p.548(d) The DES/DXAC is installed correctly (refrigerant piping, etc.).
p.548(e) Verify that the correct model number is installed and configured.
p.548NA7.5.13.2 Equipment Testing
p.548Step 1: Simulate cooling load during daytime period (e.g., by setting time schedule to
p.548include actual time and placing thermostat cooling set-point below actual temperature). Verify and document the following:
p.548(a) Supply fan operates continually.
p.548(b) If the DES/DXAC has cooling capacity, DES/DXAC runs to meet the cooling
p.548demand (in ice melt mode).
p.548(c) If the DES/DXAC has no ice and there is a call for cooling, the DES/DXAC runs in
p.548direct cooling mode.
p.548Step 2: Simulate no cooling load during daytime condition. Verify and document the
p.548following:
p.548(d) Supply fan operates as specified by the facility thermostat or control system.
p.548(e) The DES/DXAC and the condensing unit do not run.
p.548Step 3: Simulate no cooling load during morning shoulder time period. Verify and
p.548document the following:
p.548(f) The DES/DXAC is idle.
p.548Step 4: Simulate a cooling load during morning shoulder time period. Verify and
p.548document the following:
p.5483 From AEC, Distributed Energy Storage for Direct-Expansion Air Conditioners, January 27, 2005
p.548Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes