RA3.7.4.1.1 Supply and Exhaust Ventilation Systems

p.4332025 Residential Appendices has a capture area at least as large as the ventilation system inlet or outlet terminal, register or grille in all dimensions.

p.433RA3.7.4 Procedures

p.433This section describes the procedures used to verify Mechanical ventilation system airflow.

p.433RA3.7.4.1 Mechanical Ventilation Airflow Rate Measurement - Continuous Operation

p.433If multiple fans are specified to operate simultaneously to provide the total required ventilation airflow, the measurements shall be made with all applicable fans operating simultaneously.

p.433RA3.7.4.1.1 Supply and Exhaust Ventilation Systems

p.433(a) A flow measuring device that meets the applicable instrumentation requirements given in

p.433Section RA3.7.2, and RA3.7.3 shall be used to measure the ventilation airflow(s).

p.433(b) Measure and record the ventilation airflow(s).

p.433(c) If the measured total airflow is greater than or equal to the ventilation airflow rate required

p.433by the Standards or the Certificate of Compliance, the mechanical ventilation system complies. Otherwise, the mechanical ventilation system does not comply, and corrective action shall be taken.

p.433RA3.7.4.1.2 Balanced Ventilation Systems

p.433(a) A flow measuring device that meets the applicable instrumentation requirements given in

p.433Section RA3.7.2, and RA3.7.3 shall be used to measure the ventilation airflows.

p.433(b) Confirm that both the supply side and the exhaust side of the balanced system operate

p.433simultaneously in response to a shared system control.

p.433(c) Measure the airflow rate for the exhaust side of the system.

p.433(d) Measure the airflow rate for the supply side of the system.

p.433(e) Calculate the percent difference between the exhaust and supply airflow rates.

p.433(f) Calculate the average of the exhaust and the supply airflow rates.

p.433(g) If the exhaust and supply airflow rates are within 20% of each other, and the average of the

p.433exhaust and supply airflow rates is greater than or equal to the airflow rate required by the Standards or the Certificate of Compliance, the balanced ventilation system complies. Otherwise, the system does not comply, and corrective action shall be taken.

p.433(h) If the balanced system is an HRV or ERV and compliance with a recovery efficiency or fan

p.433efficacy specification is required, then also perform the verification specified in RA3.7.4.4.

p.433RA3.7.4.2 Mechanical Ventilation Airflow Rate Measurement - Intermittent Operation

p.433The Executive Director may approve intermittent mechanical ventilation systems, devices, or controls for use for compliance with field verification and diagnostic testing requirements for mechanical ventilation airflow, subject to a manufacturer providing sufficient evidence to the Executive Director that the installed mechanical ventilation systems, devices, or controls will

p.433Appendix RA3– Residential Field Verification and Diagnostic Test Protocols