p.4092025 Residential Appendices (b) Narrow spaces less than 1 inch in width at windows and door jambs, shall be filled with
p.409minimally expansive foam sealing material or SPF insulation. In cases where the manufacturer's warranty would be void if minimally expanding foam is used to seal the gap between the window frame or door jamb, the cavity must be airtight and filled with a different insulation product snuggly fitted (with limited compression) in the space.
p.409(c) Narrow spaces less than 2 inches in width, such as between studs at building corners and at
p.409the intersection of interior partition walls, shall be filled with insulation snuggly fitted into the space, with minimally expansive foam, or SPF insulation.
p.409RA3.5.6.2.2 Special Situations--Installation Prior to Exterior Sheathing or Lath
p.409(a) Hard to access wall stud cavities, such as corner channels, wall intersections, and behind
p.409tub/shower enclosures shall be insulated to the proper R-value. In most cases, this can only be completed prior to the installation of the tub/shower enclosure, the exterior sheathing, or the exterior stucco lath.
p.409(b) An air barrier shall be installed on the inside of the exterior wall(s) directly adjacent to the
p.409tub/shower enclosure.
p.409RA3.5.6.2.3 Special Situations--Obstructions
p.409(a) SPF insulation shall be applied to fully seal around wiring and plumbing.
p.409(b) SPF insulation shall be applied to fully seal between the sheathing and the rear of electrical
p.409boxes and telephone boxes.
p.409(c) In cold climates, where water pipes may freeze (Climate Zones 14 and 16), pipes shall have at
p.409least 2/3 of the insulation between the water pipe and the outside surface of the exterior wall. If the pipe is near the exterior finish assembly layers, as much insulation as possible shall be placed between the pipe and the exterior assembly material.
p.409RA3.5.6.2.4 Special Situations--Rim Joists
p.409(a) All rim-joists shall be insulated to the same R-Value as the adjacent walls.
p.409(b) The insulation shall be installed without gaps or voids.
p.409RA3.5.6.2.5 Special Situations--Kneewalls and Skylight Shafts
p.409(a) Framing for kneewalls and skylight shafts that separate conditioned from unconditioned
p.409space shall be insulated to meet or exceed the wall R-value specified on the Certificate of Compliance, and all other required compliance documentation.
p.409(b) Kneewalls within conditioned space do not need to be insulated.
p.409(c) Steel-framed kneewalls and skylight shafts shall meet or exceed the mandatory minimum
p.409insulation requirements and external surfaces of steel studs shall be covered with continuous insulation unless otherwise specified on the Certificate of Compliance using correct U-factors from Joint Appendix JA4, Table 4.3.4 (or U-factors approved by the Commission Executive Director).
p.409Appendix RA3– Residential Field Verification and Diagnostic Test Protocols