RA3.5.6.1.6 Certificates and Availability

p.4082025 Residential Appendices provided. The SPF applicator shall also make available supporting documentation showing the certified R-value per inch.

p.408RA3.5.6.1.6 Certificates and Availability

p.408All provisions of Residential Appendix RA2 shall be met. All compliance documentation shall be completed, signed by the SPF applicator, and a measuring probe or similar device shall be available at the building site for the ECC-rater's verification inspection. Note: The ECC-rater shall not verify compliance credit without these completed forms.

p.408RA3.5.6.2 Wall Insulation

p.408(a) SPF insulation shall be applied to provide an air-tight envelope to the outdoors and between

p.408adjoining cavity surfaces of conditioned and unconditioned space, such as the: attic, garage, and crawl space. Special attention shall be paid to plumbing and wiring penetrations through the top plates and bottom plate framing, and electrical boxes that penetrate the sheathing and the sheathing seal to the top and bottom plate framing.

p.408(b) Bottom plates of framed and non-framed assemblies shall be sealed to the ground subfloor or

p.408slab, and above ground subfloor.

p.408(c) SPF insulation installation shall uniformly cover the cavity side-to-side and end-to-end and

p.408shall be installed to cover and form an air barrier on the framing at the top, bottom, and sides of each cavity.

p.408Filling of Framed Assemblies: ccSPF insulation is not required to fill the cavities of framed assemblies provided the installed thickness of insulation conforms to compliance documentation and that the bottom and top plates of vertical framing and both ends of horizontal framing, including band and rim joists, are sprayed to completely fill the cavity adjacent to and in contact with the framing to a distance of 2.0 inches away from the framing for ocSPF insulation, or filled to the thickness meeting ASTM testing as an air barrier.

p.408Filling of Framed Assemblies: ocSPF insulation shall completely fill cavities of 2x4 inch framing or less. Cavities greater than 2x4 inch framing dimensions may be filled to the thickness that meets the required R-value used for compliance provided that the bottom and top plates of vertical framing and both ends of horizontal framing, including band and rim joists, are sprayed to completely fill the cavity adjacent to and in contact with the framing to a distance of 5.5 inches away from the framing for ocSPF insulation, or filled to the thickness meeting ASTM testing as an air barrier.

p.408Air Barrier: ccSPF installed as an air barrier shall be 2.0 inches in thickness. ocSPF installed as an air barrier shall be a minimum of 5.5 inches in thickness. Alternatively, ccSPF and ocSPF insulation shall be installed at a thickness that meets an air permeance no greater than 0.02 L/s-m2 at 75 Pa pressure differential when tested in accordance with ASTM E2178 or ASTM E283.

p.408RA3.5.6.2.1 Narrow-Framed Cavities

p.408(a) Non-standard width cavities shall be filled with SPF insulation at a depth consistent with the

p.408SPF thickness required to achieve the specified R-value.

p.408– Residential Field Verification and Diagnostic Test Protocols