RA3.5.3.3.6 RESERVED

p.3892025 Residential Appendices 16", and no further than 8" from the end of the batt. Batts that are directly stapled through the insulation material to the roof deck should maintain the batt uniformly against the roof deck with limited compression.

p.389(b) When the batt thickness nominally exceeds the depth of the roof framing members, full-

p.389width batts must be used, and the batt shall be secured as described in (a). Full depth insulation coverage at the bottom of the roof framing member is not required as part of the QII inspection process.

p.389(c) For vented attics, below deck batt or blanket insulation shall be installed in a manner that

p.389does not obstruct eave, ridge, or eyebrow vents to allow for adequate attic ventilation. The required net free ventilation area of all eave and roof vents shall be maintained. Eave vent baffles shall be installed to prevent air movement under or into the batt.

p.389RA3.5.3.3.6 RESERVED

p.389RA3.5.3.4 Raised Floors

p.389(a) Batt and blanket insulation shall be correctly sized to fit snugly at the sides and ends.

p.389(b) Batt and blanket insulation shall be cut to fit properly without gaps. Insulation shall not be

p.389doubled-over or compressed.

p.389(c) Batt and blanket insulation shall be in contact with the air barrier - usually the subfloor.

p.389RA3.5.3.4.1 Homes with Floors Over Garage

p.389(a) Batt and blanket insulation shall be correctly sized to fit snugly at the sides and ends, but not

p.389be so large as to buckle.

p.389(b) Batt and blanket insulation shall be cut to fit properly without gaps. Insulation shall not be

p.389doubled-over or compressed.

p.389(c) Batt and blanket insulation shall be in contact with the air barrier - usually the subfloor.

p.389(d) On floors that are over garages, or where there is an air space between the insulation and the

p.389subfloor, the rim joist shall be insulated.

p.389(e) Batt and blanket insulation shall be cut to butt-fit around wiring and plumbing, or be split

p.389(delaminated) so that one layer can fit behind the wiring or plumbing, and one layer fit in front.

p.389(f) Faced batts or blankets shall be placed toward the living space and be in contact with the

p.389underside of the floor sheathing. Continuous support shall be provided to keep the facing in contact with the floor sheathing. The insulation shall be properly supported by stapling of flanges, netting or other method approved by the manufacturer for the product.

p.389(g) Batt and blanket insulation shall be properly supported to avoid gaps, voids, and

p.389compression.