RA3.5.3.2.4 Special Situations--Rim Joists

p.3862025 Residential Appendices RA3.5.3.2.4 Special Situations--Rim Joists

p.386(a) All rim-joists shall be insulated to the same R-value as the adjacent walls.

p.386(b) The insulation shall be installed without gaps, voids, or compression.

p.386RA3.5.3.2.5 Special Situations--Kneewalls and Skylight Shafts

p.386(a) Framing for kneewalls and skylight shafts that separate conditioned from unconditioned

p.386space shall be insulated to meet or exceed the wall R-value specified on the Certificate of Compliance, and all other required compliance documentation.

p.386(b) The insulation shall be installed without gaps or compression.

p.386(c) Steel-framed kneewalls and skylight shafts, external surfaces of steel studs shall meet or

p.386exceed the mandatory minimum insulation requirements and be covered with continuous insulation unless otherwise specified on the Certificate of Compliance using correct U-factors from Joint Appendix JA4, Table 4.3.4 (or U-factors approved by the Commission Executive Director).

p.386(d) The backside of air permeable insulation exposed to the unconditioned attic space shall be

p.386completely covered with a continuous air barrier.

p.386(e) The house side of the insulation shall be in contact with the drywall or other wall finish.

p.386(f) The insulation shall be supported so that it will not fall down by either friction fitting to the

p.386framing, inset or face stapling of flanges, or using other support such as netting.

p.386(g) Insulation for all kneewall and skylight shafts shall be completely enclosed by vertical and

p.386horizontal framing, including horizontal plates at top and bottom of the insulation.

p.386RA3.5.3.2.6 Special Situations--HVAC/Plumbing Closet

p.386Walls of interior closets for HVAC and/or water heating equipment, which require combustion air venting, shall be insulated to at least the same R-value as other demising walls (i.e., walls separating conditioned space and attached garage), or as specified on the Certificate of Compliance.

p.386RA3.5.3.2.7 Special Situations--Double Walls and Framed Bump-Outs

p.386(a) Insulation shall fill the entire cavity; or, an additional air barrier shall be installed inside the

p.386double wall or bump-out and in contact with the insulation so that the insulation fills the cavity formed with the additional air barrier.

p.386(b) Entire double walls and framed bump-outs shall be air-tight.

p.386RA3.5.3.2.8 Special Situations--Structural Bracing, Tie-downs, Steel Structural Framing

p.386(a) Framing and bracing used for structural purposes shall be identified on plan documents with

p.386diagrams and/or design drawings.

p.386(b) Insulation shall be installed in a manner that minimizes heat loss/gain due to thermal bridging

p.386through the structural framing assembly.

p.386– Residential Field Verification and Diagnostic Test Protocols