p.6012025 Nonresidential Appendices NA7.18.1.1.2Functional Testing
p.601Step 1: Perform the required dwelling unit mechanical ventilation system verification
p.601procedure as specified by Reference Nonresidential Appendix NA2.2 to verify the dwelling unit ventilation systems conform to the requirements of Section 160.2(b)2.
p.601Step 2: Obtain ECC-Rater field verification as specified in Reference Nonresidential
p.601NA7.18.2 Dwelling Unit Enclosure Leakage Acceptance
p.601NA7.18.2.1 Construction Inspection
p.601Prior to functional testing, verify and document the following:
p.601a) Confirm the pressure boundary wall, ceiling, and floor penetrations are sealed.
p.601b) Confirm all gaps around windows and doors are sealed.
p.601c) Confirm all chases are sealed at floor level using a hard cover and the hard cover is
p.601sealed.
p.601NA7.18.2.2 Functional Testing
p.601Step 1: Perform the dwelling unit envelope air leakage procedure as specified by
p.601Reference Nonresidential Appendix NA2.3 to verify the dwelling unit ventilation airflow conforms to the requirements of Section 160.2(b)2.
p.601Step 2: Obtain ECC-Rater field verification as specified in Reference Nonresidential
p.601NA7.18.3 Central Ventilation System Duct Leakage Acceptance
p.601The objective of this procedure is to verify the leakage of a new central ventilation duct system that serves multiple dwelling units and provides continuous airflows or is part of a balanced ventilation system. The duct leakage shall be determined by pressurizing the entire duct system ducts to 50 Pa (0.2 inches water) with respect to outside for ducts serving more than six dwelling units, and to 25 Pa (0.1 inches water) with respect to outside for ducts serving two to six dwelling units. The following procedure shall be used for the fan pressurization tests:
p.601Test procedure, based on ASTM E1554/1554M-13 (2018) Method D – Total duct leakage
p.601test.
p.601NA7.18.3.1 Construction Inspection
p.601Prior to functional testing, verify and document the following:
p.601a) Confirm windows and other openings are open to connect the building to the
p.601outside.
p.601b) Confirm HVAC dampers are in their normal operating positions (NOP).
p.601Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes