p.3122025 Residential Appendices (d) At the request of the builder or the builder’s authorized representative, a ECC-Rater shall
p.3132025 Residential Appendices (a) Quality Installation of Insulation measure requires inspection of the air barrier and
p.312randomly select one dwelling unit from the “closed” sample group for field verification and diagnostic testing. If the dwelling unit meets the compliance requirements, this “tested” dwelling and also each of the other “not-tested” dwellings in the group shall receive a registered Certificate of Verification.
p.313inspection of the insulation behind tubs and showers at framing rough-in. Verification of the wall, floor and ceiling insulation must be completed prior to drywall installation. Attic insulation installation may require follow-up verification.
p.313(b) Buried Ducts measure requires verification of the duct design prior to verification of the
p.313attic insulation.
p.312RA2.6.3.4 Sampling of an “Open” Group of Up to Five Dwellings
p.313(c) Duct Surface Area requires verification of the duct design prior to installation of the attic
p.312The following criteria shall be met as prerequisite to attaining verification compliance for the group:
p.313insulation.
p.313The ECC-Rater, with no direction from the installer or builder, shall randomly select one dwelling unit from a “closed” sample group for field verification and diagnostic testing upon receiving the builder’s or builder representative’s request for verification of that group. Alternatively, the ECC- Rater shall randomly select one dwelling unit from the dwellings currently entered into an “open” sample group upon receiving the builder’s or builder representative’s request for verification of that group. The ECC-Rater shall diagnostically test and field verify the selected dwelling unit. The ECC-Rater shall enter the test and/or field verification results into the ECC-Provider data registry regardless of whether the results indicate a pass or fail. If the test fails, then the failure must be entered into the Provider’s data registry even if the installer immediately corrects the problem. In addition, the procedures in Section RA2.6.4 shall be followed.
p.312(a) At least one dwelling unit from the sample group has been identified. A maximum of five
p.312dwellings are allowed to be included in an “open” sample group for compliance.
p.312(b) Installation of all the measures that require verification shall be completed in all the
p.312dwellings that are entered in the group, and registration of the Certificates of Installation for all the dwellings entered in the group has been completed.
p.312(c) At the request of the builder, or the builder’s authorized representative, an ECC-Rater
p.312shall randomly select one dwelling unit from those currently entered into the “open” sample group for field verification and diagnostic testing. If the dwelling unit meets the compliance requirements, the “tested” dwelling and each of the other “not tested” dwellings currently entered into the group shall receive a registered Certificate of Verification. If less than five dwelling units have been entered into the group, the group shall be allowed to remain “open” and eligible to receive additional dwelling units. Dwelling units entered into the “open” group subsequent to the compliant verification of the “tested” dwelling shall also receive a registered Certificate of Verification as a “not tested” dwelling subject to receipt of the registered Certificate of Installation by the ECC- Provider data registry for the dwelling. The group shall be “closed” when it reaches the limit of five dwellings or when the six month limit for “open” groups has been exceeded, or when the builder requests that the group be closed.
p.313If field verification and diagnostic testing determines that the requirements for compliance are met, the ECC-Rater shall enter the test results into the ECC-Provider data registry. Whereupon the Provider shall make available to the ECC-Rater, the builder, the enforcement agency, and other approved users of the ECC-Provider data registry, a registered copy of the Certificate of Verification for the “tested” dwelling, and for all other “not tested” dwelling units entered in the group at the time of the sample test. The registered Certificate of Verification shall report the successful diagnostic testing results and conclusions regarding compliance for the tested dwelling unit. The registered Certificate of Verification shall also provide:
p.313(a) Building permit number for the dwelling unit.
p.312RA2.6.3.5 Additional Requirements Applicable to Group Sampling Procedures
p.313(b) Registration Number that conforms to the numbering convention specified in Reference
p.313Joint Appendix JA7.
p.312The builder or the ECC-Rater may request removal of untested dwelling units from a group by notifying the ECC-Provider prior to selection of the dwelling sample that will be tested from an “open” or “closed” group and shall provide justification for the change. Removed dwelling units shall be field verified and diagnostically tested individually or shall be included in a subsequent group for sampling.
p.313(c) Group Number that conforms to the numbering convention specified in Reference Joint
p.313(d) Time and date stamp of the Provider’s issuance of the registered Certificate of
p.313Verification.
p.312There are exceptions to the requirement to have completed Certificate of Installation data entered into the ECC-Provider data registry prior to selection of the dwelling unit to be tested in a group. Some measures require multiple verifications during the construction process. A sample group is not required to be closed before field verification and diagnostic testing can begin for the following measures. For these measures the ECC-Rater is allowed to randomly select the dwelling unit to be field verified from those that are at the proper stage of construction to enable the first of the multiple verifications to be completed.
p.313(e) Provider’s logo, water mark, or official seal.
p.313(f) Indication that the dwelling was a “tested” dwelling or was a “not-tested” dwelling in a
p.313sample group.
p.313Whenever the builder changes subcontractors who are responsible for a feature that is being diagnostically field verified and tested, the builder shall notify the ECC-Rater of the subcontractor change and terminate sampling for any affected groups. All dwelling units utilizing features that require verification for compliance that were installed by previous subcontractors or were
p.312Appendix RA2– Residential Field Verification and Diagnostic Testing Documentation Proceduresp.313
p.313Appendix RA2– Residential Field Verification and Diagnostic Testing Documentation Procedures