NA7.5.3.1 Construction Inspection

p.5332025 Nonresidential Appendices (b) NA7.5.3 procedures are applicable to new space conditioning systems in newly

p.533constructed buildings and to new or altered space conditioning systems in existing buildings.

p.533(c) NA7.5.3 procedures shall be used by installers, ATTs, and others who are required to

p.533perform acceptance testing of air distribution systems in accordance with Standards §120.4(g), §141.0(b)2Dii, §160.3(c)2Hi, and §180.2(b)2Biic.

p.533(d) Table NA7.5.3-1 provides a summary of the duct leakage acceptance test protocols

p.533and the compliance criteria.

p.533NA7.5.3.1 Construction Inspection

p.533Prior to Functional Testing on new duct systems, verify and document the following:

p.533(a) Duct connections meet the requirements of Standards §120.4.

p.533(b) Specify choice of drawbands.

p.533(c) Flexible ducts are not constricted in any way.

p.533(d) Duct leakage tests shall be performed before access to ductwork and connections

p.533are blocked.

p.533(e) Joints and seams are properly sealed according to the requirements of Standards

p.533§120.4.

p.533(f) Joints and seams are not sealed with cloth back rubber adhesive tape unless used

p.533in combination with Mastic and drawbands. Cloth backed tape may be used if tape has been approved by the CEC. Ducts are fully accessible for testing.

p.533(g) Insulation R-Values meet the minimum requirements of §120.4(a). Insulation is

p.533protected from damage and suitable for outdoor service if applicable as specified by Standards §120.4(f).

p.533Prior to Functional Testing on all new and existing duct systems, visually inspect to verify that the following locations have been sealed:

p.533(h) Connections to plenums and other connections to the forced air unit;

p.533(i) Refrigerant line and other penetrations into the forced air unit;

p.533(j) Air handler door panel (do not use permanent sealing material, metal tape is

p.533acceptable);

p.533(k) Register boots sealed to surrounding material; and

p.533(l) Connections between lengths of duct, as well as connections to takeoffs, wyes,

p.533tees, and splitter boxes.

p.533NA7.5.3.2 Functional Testing

p.533Perform duct leakage test to verify the duct leakage conforms to the requirements of Standards §120.4(g), §141.0(b)2Dii, §160.3(c)2Hi, and §180.2(b)2Biic.

p.533Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes