p.5532025 Nonresidential Appendices as specified by Original Equipment Manufacturer (OEM) start-up manuals and sequence of operation.
p.553(c) Cooling tower fan control sequence, including tower design wetbulb temperature
p.553and approach, is available and documented in the building documents.
p.553(d) The following temperature sensors are installed as specified by the plans: outdoor
p.553air dry-bulb, outdoor air wet-bulb, entering condenser water, and leaving chilled water. Note any discrepancies.
p.553(e) All ambient dry bulb temperature, relative humidity, and pressure sensors used by
p.553controller are factory calibrated within 2% of a calibrated reference sensor. Attach a copy of calibration certificate or field verification results.
p.553(f) Document the current outdoor air dry bulb and wet bulb temperatures, entering
p.553condenser water temperature, and leaving chilled water temperature readings from the control system.
p.553NA7.5.16.2 Functional Testing
p.553(a) The system cooling load must be sufficiently high to run the test. If necessary,
p.553artificially increase the evaporator load to perform the functional tests or wait until a time of stable chiller operation. If necessary, reverse Steps 1 and 2 in the test based on atmospheric conditions and buildings loads.
p.553(b) If testing in cold ambient conditions, ensure that freeze protection controls are
p.553installed and functional to prevent equipment damage.
p.553(c) If the actual control sequence differs significantly from that implied by the tests
p.553and/or has already been tested during the building commissioning process, attach a description of the control sequence, a description of the tests that were done to verify the system operates according to the sequence, the test results, and a plot of associated trend data.
p.553(d) Identify the reset control parameter.
p.553Step 1: Adjust the reset control parameter to decrease the condenser water supply
p.553temperature toward the lower supply temperature limit. Allow time for the system to stabilize. Verify and document the following:
p.553(a) Condenser water supply temperature controls modulate as intended.
p.553(b) Actual condenser water supply temperature decreases to meet the new setpoint
p.553within ±2oF.
p.553(c) Cooling tower fan(s) stage properly and/or adjust speed accordingly to meet higher
p.553setpoint.
p.553(d) Chiller load amperage decrease.
p.553Step 2: Adjust the reset control parameter to increase the condenser water supply
p.553temperature toward the upper supply temperature limit.
p.553Verify and document the following:
p.553(e) Condenser water supply temperature controls modulate as intended.