p.5502025 Nonresidential Appendices (t) Number of Tanks
p.550(u) Storage Capacity per Tank (ton-hours)
p.550(v) Storage Rate (tons)
p.550(w)Minimum Charging Temperature
p.550(x) Discharge Rate (tons)
p.550NA7.5.14.2 Functional Testing
p.550Acceptance testing also shall be conducted and documented on the Certificate of Acceptance in two parts: the TES System Design Verification part and the TES System Controls and Operation Verification part.
p.550In the TES System Design Verification part, the installing contractor shall certify the following information, which verifies proper installation of the TES System consistent with system design expectations:
p.550(a) Chiller(s) start-up procedure has been completed.
p.550(b) System fluid test and balance has been completed.
p.550(c) Air separation and purge has been completed.
p.550(d) Fluid (e.g., glycol) has been verified at the concentration and type indicated on the
p.550design documents.
p.550(e) The TES system has been fully charged at least once and the charge duration
p.550noted.
p.550(f) The system has been partially discharged at least once and the discharge duration
p.550noted.
p.550(g) The system is in a partial charge state in preparation for the TES System Controls
p.550and Operation Verification part.
p.550(h) The schedule of operation has been activated as designed.
p.550(i) Mode documentation describes the state of system components in each mode of
p.550operation.
p.550In the TES System Controls and Operation Verification part, the installing contractor also shall complete the following acceptance testing to ensure the TES System is controlled and operates consistent with the compliance simulation. The installing contractor shall convey the results of the testing to the enforcement agency using the Certificate of Acceptance.
p.550(a) Verify that the TES system and the chilled water plant is controlled and monitored
p.550by an energy management system (EMS).
p.550(b) Indicate the method of simulation that will be used during the test. Either manual
p.550selection of each operating mode or the use of an EMS by inputting the schedule as indicated by the designer.
p.550Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes