NA7.4.3.4 Documentation at Occupancy:

p.5252025 Nonresidential Appendices (b) When controls are installed with the dynamic glazing, it should be verified that it

p.525meets the exact operation specifications of the dynamic glazing installation, functional and testing instructions.

p.525(c) After dynamic glazing inspection is complete, ensure the Certificate of Acceptance

p.525form is completed and including the signature of the Declaration Statements; and

p.525(d) Provide certificates and additional copies to the builder, enforcement agency and

p.525building owner at occupancy.

p.525NA7.4.3.4 Documentation at Occupancy:

p.525The following documentation shall be made available to the responsible party of construction or building owner at occupancy;

p.525(a) A completed and signed Certificate of Installation and Certificate of Acceptance,

p.525form(s);

p.5251. If supplied by the manufacturer, a copy of the manufacturer’s warranty and user manual.

p.525NA7.4.4 Clerestories for PAF

p.525NA7.4.4.1 Procedures

p.525These procedures detail the installation and verification protocols necessary to meet acceptance requirements of clerestory fenestrations for PAF. In addition, the responsible person shall fill out the Certificate of Installation and the Certificate of Acceptance. The responsible person shall verify the clerestory fenestration to be installed matches the energy compliance documentation (Certificate of Compliance) and building plans. A copy of the Installation and Acceptance certificate shall be given to the building owner and the enforcement agency for their records.

p.525For buildings with up to seven (7) clerestory fenestration units claiming the Clerestory Fenestration PAF, all clerestory fenestration units shall be tested. For buildings with more than seven (7) clerestory fenestration units claiming the PAF, random sampling may be done to select the seven clerestory fenestration units. If any of the clerestory fenestration units in the sample group or seven clerestory fenestration units fails the acceptance test, another group of seven clerestory fenestration units must be tested.

p.525NA7.4.4.2 The Responsible Person or Installer Shall Meet the Following Protocols before Installation:

p.525(a) Verify the height of the clerestory fenestration’s head height and glazing height

p.525match the building plans;

p.525(b) Installation of clerestory fenestration shall meet the manufacturer’s installation

p.525instructions;

p.525(c) After the installation the installer completes and signs the Declaration Statement

p.525on the Certificate of Installation. A signed copy of the Certificate(s) shall remain at the job site for verification by the building inspector.

p.525Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes