p.5902025 Nonresidential Appendices Off
p.590Unloaded
p.590Partially loaded
p.590Fully loaded
p.590Short cycling (loading and unloading more often than once per minute)
p.590Blow off (venting compressed air at the compressor itself)
p.590NA7.13.1.2 Functional Testing
p.590Step 1: As specified by the test methods outlined in the Construction Inspection, verify
p.590that these methods have been employed, so that the states of the compressors and the current air demand (as measured by a flow sensor or otherwise inferred by system measurements) can be observed and recorded during testing.
p.590Step 2: Run the compressed air supply system steadily at as close to the expected
p.590operational load range as can be practically implemented, for a duration of at least 10 minutes.
p.590Step 3: Observe and record the states of each compressor and the current air demand
p.590during the test.
p.590Step 4: Confirm that the combinations of compressors states meet the following criteria:
p.590(a) No compressor exhibits short-cycling (loading and unloading more often than once
p.590per minute).
p.590(b) No compressor exhibits blowoff (venting compressed air at the compressor itself).
p.590(c) For new systems, the trim compressors shall be the only compressors partially
p.590loaded, while the base compressors will either be fully loaded or off by the end of the test.
p.590NA7.13.2 Compressed Air Monitoring
p.590Acceptance tests for compressed air monitoring installed in accordance with Section 120.6(e)3.
p.590NA7.13.2.1 Construction Inspection
p.590Verify and document the following monitoring system capabilities prior to functional testing:
p.590(a) Measurement of header or compressor discharge pressure.
p.590(b) Measurement of amps or power of each compressor.
p.590(c) Measurement or determination of airflow in cfm.
p.590(d) Data logging of pressure, power, airflow, and calculated compressed air system
p.590specific efficiency in kW/100 cfm at intervals of 5 minutes or less.
p.590(e) Maintained data storage.
p.590Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes