p.4152025 Residential Appendices RA3.5.7.1.2 R-value Measurement Equipment
p.415The ECC-raters shall verify the installed thickness of insulation in all SIP panels and locations on walls, roof/ceilings, and floors, and to ensure that insulation levels and installation integrity meet the R-value specified on the Certificate of Compliance, and all other required compliance documentation.
p.415RA3.5.7.1.3 Certificates
p.415All provisions of Residential Appendix RA2 shall be met. An Insulation Certificate of Installation signed by the installer shall be provided that states the installation is consistent with the Certificate of Compliance, plans and specifications for which the building permit was issued. The SIP installer shall also complete the applicable sections of the Certificate of Installation form and attach a product specification or data sheet for every insulation material used.
p.415RA3.5.7.1.4 Certificates and Availability
p.415All provisions of Residential Appendix RA2 shall be met. The Insulation Certificate of Installation, with insulation material labels or specification/data sheets attached, signed by the SIP installer, shall be available on the building site for each of the ECC-rater's verification inspections. Note: The ECC-rater cannot verify compliance credit without these completed forms.
p.415RA3.5.7.2 Wall Insulation
p.415(a) Connections of wall panels shall be sealed, caulked, foamed, or taped (i.e., SIP tape) to
p.415provide a substantially air-tight envelope to the outdoors, attic, garage, and crawl space. All plumbing and wiring penetrations through the top and bottom of panels, and electrical boxes that penetrate the SIP sheathing shall be sealed. All gaps in the air barrier shall be caulked or sealed with minimally expansive foam or taped (i.e., SIP tape).
p.415(b) Bottom connections of wall panels shall be sealed to the ground subfloor or slab, and above
p.415ground subfloor.
p.415(c) Insulation shall uniformly fit across the plane of the wall and taping (i.e., SIPs tape), caulking
p.415or sealing of all joints and seams of panel joints (i.e., spline connections) shall be maintained to be considered as the air barrier.
p.415RA3.5.7.2.1 Special Situations--Obstructions
p.415(a) Penetrations and obstructions to the SIP shall be completely caulked and sealed.
p.415(b) Insulation shall fill between the sheathing and the rear of electrical boxes and phone boxes.
p.415RA3.5.7.2.2 Special Situations--Rim Joists
p.415(a) All rim-joists shall be insulated to the same R-value as the adjacent walls.
p.415(b) The insulation shall be installed without gaps and voids.