p.4062025 Residential Appendices Filling of Framed Assemblies: ocSPF insulation shall completely fill cavities of 2x4 inch framing or less. Cavities greater than 2x4 inch framing dimensions may be filled to the thickness that meets the required R-value used for compliance provided that the bottom and top plates of vertical framing and both ends of horizontal framing, including band and rim joists, are sprayed to completely fill the cavity adjacent to and in contact with the framing to a distance of 5.5 inches away from the framing for ocSPF insulation, or filled to the thickness meeting ASTM testing as an air barrier.
p.406Air Barrier: ocSPF installed as an air barrier shall be a minimum of 5.5 inches in thickness; alternatively, ocSPF insulation shall be installed at a thickness that meets an air permeance no greater than 0.02 L/s-m2 at 75 Pa pressure differential when tested in accordance to ASTM E2178 or ASTM E283.
p.406Table RA3.5-1: Required Thickness (inches) of SPF Insulation to Achieve Specified R-values
| Equivalent R-Values for SPF insulation | 11 | 13 | 15 | 19 | 21 | 22 | 25 | 30 | 38 |
|---|---|---|---|---|---|---|---|---|---|
| Required thickness of ccSPF insulation @ R5.8/inch | 2.00 | 2.25 | 2.75 | 3.50 | 3.75 | 4.00 | 4.50 | 5.25 | 6.75 |
| Required thickness of ocSPF insulation @ R3.6/inch | 3.0 | 3.5 | 4.2 | 5.3 | 5.8 | 6.1 | 6.9 | 8.3 | 10.6 |
p.406RA3.5.6.1.3 Requirements for Walls, Ceilings and Floors
p.406(a) Materials shall comply with, and be installed in conformance with, all applicable building
p.406codes for building. California Building Code (including, but not limited to, California Electric Code Section 719) and installed to meet all applicable fire codes.
p.406(b) Materials shall meet California Quality Standards for Insulating Material, Title 24, Part 12,
p.406Chapter 4, Article 3, listed in the California Department of Consumer Affairs Consumer Guide and Directory of Certified Insulating Materials.
p.406(c) Materials shall comply with flame spread index and smoke developed index requirements of
p.406the CBC, Title 24, Part 2, Section 2603.5.4.
p.406(d) The installer shall determine, and the ECC-rater shall verify, that the manufacturer’s nominal
p.406insulation thickness has been installed and certified and that all requirements of the Certificate of Verification have been met.
p.406(e) The installer shall determine, and the ECC-rater shall verify, that insulation is in substantial
p.406contact with the assembly air barrier. When SPF insulation is being used to provide air barrier control, the SPF insulation must cover and be in contact with the entire surface of the framing, filling the cavity to a distance away from the framing specified in "Filling of Framed Assemblies" above.
p.406(f) SPF insulation shall be applied by SPF applicators trained and experienced in the use and
p.406maintenance of high-pressure, plural-component equipment. SPF applicators shall be certified by the SPF insulation manufacturer for the application of SPF insulation systems.
p.406– Residential Field Verification and Diagnostic Test Protocols