NA7.20.1.1.3 Functional Testing (Option B: Supercritical Operation)

p.6092025 Nonresidential Appendices Step 6: Restore setpoints:

p.6102025 Nonresidential Appendices

p.610(This page intentionally left blank.)

p.609(a) Restore any heat reclaim or defrost functionality that was turned off to allow

p.609testing.

p.609(b) Reset the minimum condensing temperature setpoint if it was adjusted during

p.609Step 5.

p.609(c) Reset adiabatic mode controls to original values.

p.609NA7.20.1.1.3 Functional Testing (Option B: Supercritical Operation) Planning: Ambient conditions must be sufficiently above the critical point to operate supercritically. Account for weather conditions in scheduling testing by, if necessary, artificially increasing or decreasing evaporator loads in order to perform the Functional Testing at typical system conditions.

p.609Step 1: Verify mechanical controls and other strategies will not affect tests:

p.609(a) Turn off any heat reclaim controls and any intermittent defrost pressure offset

p.609strategies that would affect gas cooler setpoint control.

p.609(b) If testing an adiabatic gas cooler, adjust setpoints to ensure that the gas cooler

p.609stays in “dry” mode or “precool” mode consistently throughout the test.

p.609Step 2: Operate in supercritical mode and verify pressure control:

p.609(a) Observe operation for at least 30 minutes or reference control system history or

p.609visual trends to verify the gas cooler holdback valve modulates its opening in response to changes in ambient dry bulb or precool air temperature resulting in a change in gas cooler pressure. Reference the original equipment manufacturer operating manual or sequence of operation descriptions to confirm the observed variation in the pressure setpoint is consistent with the design control strategy.

p.609Step 3: Restore setpoints:

p.609(a) Restore any heat reclaim or defrost functionality that was turned off to allow

p.609testing.

p.609(b) Reset adiabatic mode controls to original values.

p.609Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processesp.610

p.610Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes