p.555NA7.5.18 Cooling Tower Conductivity Controls
p.555The following acceptance tests apply to all open- and closed-circuit cooling towers.
p.555NA7.5.18.1 Construction Inspection
p.555Prior to functional testing, verify and document the following:
p.555(a) The conductivity controls, makeup water flow meter(s), and overflow alarms are
p.555installed as specified on the plans.
p.555(b) Maximum achievable cycles of concentration are documented on the NRCC
p.555MCH-E compliance document.
p.555(c) Blowdown control sequence is available and documented in the building
p.555documents.
p.555(d) Controls are programmed to automate bleed to the maximum cycles of
p.555concentration documented on the NRCC-MCH-E form.
p.555(e) Controls shall be programmed not to allow blowdown until one or more of the
p.555parameters in Table NA7 reaches the value specified in NRCC-MCH-E.
p.555Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processesp.556
p.5562025 Nonresidential Appendices Table NA-7 RECIRCULATING WATER PARAMETERS
p.556Recirculating Water Parameters Maximum Values Conductivity (micro-siemens/cm) 2970 micro-siemens/cm Total dissolved solids (ppm) 1845 ppm Total alkalinity as CaCO23 (ppm) excluding galvanized steel
p.556540 ppm
p.556Total alkalinity as CaCO3 (ppm) galvanized steel (passivated)
p.556450 ppm
p.556Calcium hardness as CACO3 (ppm) 540 ppm Chlorides as Cl (ppm) 270 ppm Sulfates (ppm) 225 ppm Silica (ppm) 135 ppm Langelier saturation index (LSI) 2.5 LSI