p.576NA7.8.3 RESERVED
p.576NA7.8.4 RESERVED
p.576NA7.8.5 Automatic Scheduling Controls Acceptance Tests
p.576NA7.8.5.1 Construction Inspection
p.576Prior to functional testing, confirm and document the following:
p.576(a) The automatic scheduling controls are shown on plan documents and are installed.
p.576(b) The control is programmed with on schedules and off schedule that matches the
p.576schedules in the construction documents. If the schedule is unknown, confirm that the programmed schedule matches the default schedule where the off schedule is from midnight to 6am and the on schedule is all other nighttime hours, seven days per week.
p.576(c) The lighting control programming including both on schedule and off schedule, for
p.576weekday, weekend, and holidays (if applicable).
p.576(d) The correct time and date are properly set in the control.
p.576NA7.8.5.2 Functional Testing
p.576Verify and document the following:
p.576(a) During daytime simulation, all controlled luminaires are turned off.
p.576(b) During nighttime simulation with the programmed occupied period, all controlled
p.576luminaires are turned on.
p.576(c) During nighttime simulation with the programmed unoccupied period, the controlled
p.576luminaires are turned off or the lighting power of controlled luminaires is reduced by at least 50 percent and no more than 90 percent.
p.576RESERVED
p.576Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processesp.577