p.5222025 Nonresidential Appendices (b) Purchase Order or Receipt:
p.5221. A copy of the purchase order or a detailed payment receipt shall be used to cross reference with the NFRC Product Label Certificate CPD number or the Fenestration Certificate of Compliance values; and
p.5222. The purchase order or a detailed payment receipt should match the energy compliance documentation and the building plans.
p.522(c) Fenestration Building Plans:
p.5221. The building plans shall list in a schedule for each fenestration product to be installed in the building.
p.522(d) Certificate of Acceptance Form:
p.5221. The acceptance form shall be filled out by the responsible party and signed; and
p.5222. The signed Certificate of Acceptance shall be submitted to enforcement agency or field inspector; and
p.5223. A copy of the Certificate of Acceptance shall be given to the building owner.
p.522NA7.4.2 Window Films
p.522NA7.4.2.1 Procedures
p.522These procedures detail the installation and verification protocols necessary to meet acceptance requirements of window films. Each window film product shall be provided with a temporary NFRC Label on the box to identify the thermal performance (e.g. U- factor, Solar Heat Gain Coefficient(SHGC), and Visible Transmittance (VT)) of each window film product being installed. The labels, an Energy Commission Default Fenestration Certificate of Compliance form or an NFRC label, shall be located at the job site for verification by the enforcement agency. In addition, the responsible person shall fill out the Installation Certificate and the Certificate of Acceptance, Fenestration Acceptance Certificate. The responsible person shall verify the thermal performance of each window film to be installed matches the energy Certificate of Compliance documentation and building plans. A copy of the Installation and Acceptance certificate shall be given to the building owner and the enforcement agency for their records.
p.522NA7.4.2.2 The Responsible Person or Installer Shall Meet the Following Protocols before Installation:
p.522(a) Verify the name of the manufacture or brand name matches with building plans;
p.522(b) From the building plans or energy compliance forms, identify the azimuth
p.522orientation in degrees or in cardinal orientation for each of the window film to be installed to ensure the correct window film specifications are installed in the appropriate orientation;
p.522(c) Verify the temporary NFRC label on the box for each window film’s U-factor, Solar
p.522Heat Gain (SHGC) and Visible Transmittance (VT) matches the energy
p.522Appendix NA7 – Installation and Acceptance Requirements for Nonresidential Buildings and Covered Processes