p.227JA7.8.4 Rescinding Approval (Deactivation) of Data Registries
p.227The Commission may rescind approval of Data Registries through various means as described in this section.
p.227A revision to the functionality of a Data Registry to discontinue a working or contractual relationship between the Data Registry and an External Digital Data Source Provider:
p.227(a) Shall not be a procedure that initiates deactivation of the Data Registry.
p.227(b) Shall use the approval procedures specified in Sections JA7.8.3.1 or JA7.8.3.2, as
p.227applicable.
p.227JA7.8.4.1 Procedures that Initiate Deactivation
p.227(a) All Data Registries are deactivated when the Standards undergo substantial changes,
p.227usually occurring with each Standards update. However, the Data Registry shall remain approved to provide document registration for projects that have been permitted under the prior versions of the Standards.
p.227(b) Any Data Registry can be deactivated by a letter from the Registration Provider
p.227requesting that the Data Registry be deactivated. The deactivation request shall briefly describe the reasons that justify the need for deactivation.
p.227(c) The Executive Director may at any time, including upon petition by any party or
p.227recommendation by Commission staff, initiate a review of a Data Registry approval according to the steps outlined in Section JA7.8.4.2 below. The intent is to provide a means whereby serious Data Registry errors, violations of JA7, flawed numeric results, or improper registered document output not discovered in the Data Registry approval process can be verified, and a corrective course of action determined. Also, the intent is to provide ample opportunity for the Commission, the Registration Provider, and all interested parties to evaluate any alleged errors in the Data Registry functionality.
p.227JA7.8.4.2 Challenging a Data Registry and Initiating Deactivation
p.227A description of the process for challenging a Data Registry or initiating a deactivation procedure follows:
p.227(a) Any party may request a review of a Data Registry approval by submitting a petition
p.227to the Energy Commission's Executive Director. petition shall: 1. State the name of the Data Registry that contains the alleged errors or violations of the Registration Provider’s obligations under JA7; 2. Identify concisely the nature of the alleged errors or violations of the Registration Provider’s obligations under JA7 in the Data Registry that require review; 3. Explain why the alleged errors are serious enough in their effect on document registration compliance to justify a deactivation procedure; and 4. Include appropriate data electronically (in a format agreed to by the Executive Director) and/or information sufficient to evaluate the alleged errors or violations of JA7.
p.227(b) The Executive Director shall make a copy or copies of the petition or Commission
p.227Staff’s recommendation report available to the Registration Provider and interested
p.227Appendix JA7 – Data Registry Requirementsp.228
p.228parties within 30 days. Comments from interested parties shall be received within 60 days of the acceptance of the original application.
p.228(c) Within 75 days of receipt of the petition or recommendation report, the Executive
p.228Director may request any additional information needed to evaluate the alleged Data Registry errors or violations of the Registration Provider’s obligations under JA7 from the party who initiated the deactivation review process. If the additional information is incomplete, this procedure will be delayed until the initiating party submits complete information.
p.228(d) Within 75 days of receipt of the petition or recommendation report, the Executive
p.228Director may convene a workshop to gather additional information from the initiating party, the Registration Provider and interested parties. All parties will have 15 days after the workshop to submit additional information regarding the alleged Data Registry errors or alleged violations of the Registration Provider’s obligations under JA7.
p.228(e) Within 90 days after the Executive Director receives the petition or recommendation
p.228report or within 30 days after receipt of complete additional information requested of the initiating party, whichever is later, the Executive Director shall either:
p.2281. Determine that the Data Registry need not be deactivated; or
p.2282. Submit to the Energy Commission a written recommendation that the Data Registry be deactivated.
p.228(f) If the Energy Commission approves the Data Registry deactivation, it shall take
p.228effect 60 days later. During the first 30 days of the 60 day period, the Executive Director shall send out a Notice to Enforcement Agencies and Interested Parties announcing the deactivation.