p.205JA7.5.6 Project Document Configuration
p.205Data Registries shall be capable of tracking all compliance documentation and maintaining the correct associations between related documents, including revisions and completion statuses for all documents within a building project.
p.205A certificate of compliance establishes the requirements for project documentation for prescriptive and performance compliance methods.
p.205The Standards specify mandatory verification for residential projects for which there are options for compliance with the mandatory requirement. Thus, indication of the option selected for compliance with a residential mandatory measure may not be known until after a Certificate of Installation is submitted to a Data Registry to demonstrate compliance with the mandatory requirement. The Data Registry shall track when Certificate of Installation documents are registered for any mandatory measure that has an option for compliance; shall report any verification requirement that is triggered by the mandatory measure; and ensure that any required verification is completed as a condition of compliance. Refer to the Data Registry Requirements Manual for additional guidance describing residential Data Registry tracking of mandatory measure options and the required documentation for the mandatory options.
p.205JA7.5.6.1 Project Status Reports
p.205The status of completion of a project shall be reported by the Data Registry.
p.205The Data Registry shall determine the documents required for a project based on the Certificate of Compliance and maintain a project status report with a summary of the current status of completion of the required documents for the project. The project status report shall be readily accessible to authorized users of the Data Registry. Access to the report shall be facilitated by use of search parameters relevant to the project as listed in Sections JA7.5.6.1.1 and JA7.5.6.1.2.
p.205Enforcement Agencies may be authorized to enter notations into project records in data registries to communicate plan check and field inspection information to builders, designers, installers, raters and other parties to the construction project.
p.205Appendix JA7 – Data Registry Requirementsp.206
p.206The project status report shall be made available in a printable format.
p.206Minimum information requirements for the project status report shall include the following: