p.546Section 170.1 – Performance Approach
p.546A building complies with the performance approach if the energy consumption calculated for the proposed design building is no greater than the energy budget calculated for the standard design building using Commission-certified compliance software as specified by Sections 10-109, 10-116 and the Alternative Calculation Method Reference Manual.
p.546(a) Energy budget. The Energy budget is expressed in terms of long-term system cost (LSC) and source
p.546energy:
p.5465. Long-term system cost (LSC). The LSC energy budget is determined by applying the mandatory and prescriptive requirements of the standard design to the proposed design building and has two components, the Efficiency LSC and the Total LSC.
p.546A. The Efficiency LSC energy is the sum of the LSC energy for space-conditioning, water heating,
p.546mechanical ventilation, lighting and the self-utilization credit.
p.546B. The Total LSC energy is the sum of the Efficiency LSC energy and LSC energy from the
p.546photovoltaic system, battery energy storage systems (BESS), and demand flexibility.
p.5466. Source energy. The source energy budget is determined by applying the mandatory and prescriptive requirements of the standard design, except with a consumer gas or propane water heater, to the proposed design building.
p.546(b) Compliance demonstration requirements for performance standards.
p.5461. Certificate of Compliance and Application for a Building Permit. The application for a building permit shall include documentation pursuant to Sections 10-103(a)1 and 10-103(a)2 that demonstrates, using an approved calculation method, that the building has been designed so that its source energy and LSC energy consumption do not exceed the standard design energy budgets for the applicable climate zone.
p.5462. Field verification of individual dwelling unit systems. When performance of installed features, materials, components, manufactured devices or systems above the minimum specified in Section 170.2 is necessary for the building to comply with Section 170.1, or is necessary to achieve a more stringent local ordinance, field verification shall be performed in accordance with the applicable requirements in the following subsections, and the results of the verification(s) shall be documented on applicable Certificates of Installation pursuant to Section 10-103(a)3 and applicable Certificates of Verification pursuant to Section 10-103(a)5.p.547
p.546Section 170.1 – Performance Approach
p.547A. EER2/SEER2/CEER/HSPF2 Rating. When performance compliance requires installation of a
p.547space-conditioning system with a rating that is greater than the minimum rating required by Table 170.2-K or specified for the standard design, the installed system shall be field verified in accordance with the procedures specified in the applicable sections of Reference Residential Appendix RA3.
p.547B. Variable capacity heat pump (VCHP) compliance option. When performance compliance
p.547requires installation of a heat pump system that meets all the requirements of the VCHP compliance option specified in the ACM Reference Manual, the system shall be field verified in accordance with the procedures in Reference Residential Appendix RA3.4.4.3.
p.547C. Low leakage air handler. When performance compliance requires installation of a low
p.547leakage air-handling unit, the installed air handling unit shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.1.4.3.9.
p.547D. Thermal Balancing Valve. When performance compliance requires installation of thermal
p.547balancing valves with variable speed circulation pump(s), the installation shall meet the procedures specified in Reference Residential Appendix RA4.4.3.
p.547E. Heat pump—rated heating capacity. When performance compliance requires installation of
p.547a heat pump system, the heating capacity values at 47°F and 17°F shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.4.4.2.
p.547F. Dwelling unit enclosure air leakage. When performance compliance requires a building
p.547enclosure leakage rate that is lower than the standard design, the building enclosure shall be field verified in accordance with the procedures specified in Reference Residential Appendix RA3.8.
p.547G. Quality insulation installation (QII). When performance compliance requires field
p.547verification of QII, the building insulation system shall be field verified in accordance with the procedures in Reference Residential Appendix RA3.5.