(b) Dwelling unit space-conditioning and air distribution systems.

p.499b. Not economizing when it should;

p.499c. Economizing when it should not;

p.499d. Damper not modulating; and

p.499e. Excess outdoor air.

p.499viii. The FDD system shall be certified to the Energy Commission as meeting the

p.499requirements of Sections 160.3(a)2Hi through 160.3(a)2Hvii in accordance with Section 110.0 and JA6.3.

p.499I. Direct Digital Controls (DDC). Direct digital controls to the zone shall be provided as

p.499specified by Table 160.3-C.

p.499i. The provided DDC system shall meet the control logic requirements of Sections

p.499160.3(a)2E and 160.3(a)2G, and be capable of the following:

p.499ii. Monitoring zone and system demand for fan pressure, pump pressure, heating and

p.499cooling;

p.499iii. Transferring zone and system demand information from zones to air distribution system

p.499controllers and from air distribution systems to heating and cooling plant controllers;

p.499iv. Automatically detecting the zones and systems that may be excessively driving the reset

p.499logic and generate an alarm or other indication to the system operator;

p.499v. Readily allow operator removal of zone(s) from the reset algorithm;

p.499vi. For new buildings, trending and graphically displaying input and output points; and

p.499vii. Resetting heating and cooling setpoints in all noncritical zones upon receipt of a signal

p.499from a centralized contact or software point as described in Section 160.3(a)2G.

p.499J. Optimum start/stop controls. Space-conditioning systems with DDC to the zone level shall

p.499have optimum start/stop controls. The control algorithm shall, as a minimum, be a function of the difference between space temperature and occupied setpoint, the outdoor air temperature, and the amount of time prior to scheduled occupancy. Mass radiant floor slab systems shall incorporate floor temperature onto the optimum start algorithm.

p.499(b) Dwelling unit space-conditioning and air distribution systems.

p.4991. Building cooling and heating loads. Building heating and cooling loads shall be determined using a method based on any one of the following, using cooling and heating loads as two of the criteria for equipment sizing and selection:

p.499A. The ASHRAE Handbook, Equipment Volume, Applications Volume and Fundamentals

p.499Volume; or

p.499SECTION 160.3 – MANDATORY REQUIREMENTS FOR SPACE CONDITIONING SYSTEMS IN MULTIFAMILY BUILDINGS